Randridge were contracted to carry out all of the cabling of the pole mounted generators for the wind turbines at the Eemshaven wind farm. This included laying of underground cables, terminating the cables at both ends, testing and switching on. There were 90 turbines in total 87 of which having an installed capacity of 3MW and the other three 6MW.
This project is part of the Eemshaven Energyport project which consists of investments billions of Euros in new power stations; an oil terminal; a data centre; and this wind park which is the largest wind park on land in the Netherlands.